US$188 million unpaid to contractors despite booming macroeconomic growth

Date:

Business Correspondent

Zimbabwean construction firms are facing severe working capital constraints and financial distress, caught in a paradoxical squeeze between surging macroeconomic growth and crippling payment delays for completed public works, with an estimated $188 million in certified certificates remaining unpaid to local contractors.

Addressing delegates at the Zimbabwe Building Contractors Association (ZBCA) Annual Conference 2026, the association president Dr. Tinashe Manzungu highlighted the stark contradiction between national economic indicators and the commercial reality experienced by local builders.

According to ZIMSTAT data, Zimbabwe’s real GDP grew by approximately 8.29 percent in 2025, while historical national accounts show that real construction value-added increased by roughly 14.6 percent cumulatively between 2020 and 2024.

Despite this sector-wide expansion, Manzungu warned that rising activity levels have failed to translate into financially robust contractors. Many firms continue to grapple with expensive equipment procurement, inadequate working capital, and restricted access to affordable financing—challenges compounded by the massive $188 million backlog in public disbursements.

When payments stall, contractors are forced to absorb project costs, effectively converting commercial enterprises into involuntary financiers for public and private developments.

“Contractors must procure materials, mobilise equipment, pay employees and meet statutory obligations throughout project implementation. When payments are delayed, contractors effectively become involuntary financiers of projects,” Manzungu cautioned.

The ZBCA leadership acknowledged competing fiscal pressures faced by the State but issued an urgent appeal for predictable payment schedules, realistic project budgeting, and timely settlements.

Warning that commercial viability underpins long-term infrastructure delivery, Manzungu emphasized that structural reform must establish strict payment certainty.

“Timely payment to contractors is not simply settlement for completed work. It is the financial foundation upon which future infrastructure is built,” Manzungu declared, calling for constructive engagement with government ministries to resolve cash flow bottlenecks and safeguard local industry capacity.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Sanctioned Russian payments firm A7 opens in Zimbabwe amid growing financial scrutiny

By Managing Editor Russian payments company A7 has opened offices...

Finance minister proposes zero customs duty on vehicle assembly kits

By Bhekithemba Ncube Finance Minister Professor Mthuli Ncube has proposed...

Mthuli Ncube proposes cutting customs duty on electric vehicles to 10%

Business Correspondent Finance Minister Professor Mthuli Ncube has proposed reducing...

Finance minister proposes scrapping customs duty on mobile phones

Business Correspondent Government has proposed removing customs duty on cellular...